1. Maintain ISO Certification while maintaining zero major non conformances -- Met. Zero major non conformances were found during yearly ISO certification audit.
2. Failure /Root cause analysis -- Able to perform the Failure/Root cause analysis if there's a return or feedback from filed.
3. TSP kept current and updated within reasonable time frame. -- All TSP were reviewed and updated to current practice except 3x TSP were identified as OFI. The minor change of OFI TSP will be covered by the future revision.
4. Plan 2018 periodic audits on line to make sure operators are not deviating from our ASP/ TSP. -- Periodically audited CMs and no major deviating found. Electronic MI was implemented to make sure operators are performing the work based on the latest ASP/TSP.
5. Support database of testers, tooling and equipment. Conduct a risk assessment; identify what are the gaps and backup plans to meet production needs -- Standardized the Tester dashboard across all CMs and IT infrastructure list was created while Asset Manual was updated. A tester drawing library was created to support local tester maintenance. The testers were accessed based on its criticality and the spare parts will be building up based review result by tester health check project. Most of testers PC were backed up as per plan.
6. Maintain a validation master list for the site -- All the testers were validated when it's needed for all WPPL CMs.
7. Internal documentation on testers troubleshooting and knowledge transfer -- A tester library was created and tester related information/knowledge were shared/saved.
8. Efficiency improvement / metrics: Improved / exceed FPY by 10% (Goal shared with Quality) -- Overall FPY was improved, such as Alliance with new seal pack FPY was improved from low 70% to high 90%. It's exceed FPY by more than 10%.
9. To understand and bench mark test equipment performance -- Periodically review/monitor individual tester performance. Further study was carried out if there's a room for tester FPY improvement.
10.Compute current testers' performance and set improvement targets by end of Q2 (FTN, BSM, Alliance & Detectors). -- Completed tester performance review and improvement plan was carried out. The FTN tester breakdown time was significantly reduced after half yearly seal replacement plan executed.
11. Ensure tester to tester variation is consistent among functional final testers with variation of no more than 5% among similar family of testers -- Individual testers performance was periodically reviewed/monitored. The necessary actions were taken to make sure the variation keep less than 5%.